Buzy Town Hall: a 30-metre ATG installation and renovation photographs
11/11/2026
Buzy rural seniors’ hall: measurements before and after an ATE LC30 installation
11/11/2026Old church walls combine thick masonry, finishes from different periods and ventilation conditions linked to the building’s use. The Buzy church file places the Humidistop installation in this heritage setting.
Installation in July 2016
The report records installation on 19 July 2016 on the load-bearing wall on the right-hand side of the church. The geomagnetic process has a planned coverage diameter of 60 metres, or 30 metres around the device. Presented as an ATG wall-drying polarity inverter without electricity, this installation is separate from the Town Hall project.
A recorded starting condition
The file includes photographs and measurements taken during installation. They preserve an initial record for later comparison. The selected photographs show the church and its walls, without a view of the device.
Building-related recommendations
The report recommends airing the church, removing damaged plaster and checking the roof. Finishes and possible water ingress must therefore also be considered. The available legible documents establish the building, installation date and planned diameter. They do not yet provide numerical follow-up results, so no final drying percentage is stated.